SAKILA, ZALFA PUTU AYU (2023) KONSEP LEAN CONSTRUCTION UNTUK MEMONITORING WASTE DAN MENGESTIMASI BIAYA PADA PROYEK PEMBANGUNAN GEDUNG DIALISA DAN HCU RSUD PROF. DR. MARGONO SOEKARJO PURWOKERTO. S1 thesis, UNIVERSITAS MUHAMMADIYAH PURWOKERTO.

Text
ZALFA PUTU AYU SAKILA_COVER.pdf

Download (30MB)
Text
ZALFA PUTU AYU SAKILA_BAB I.pdf

Download (879kB)
Text
ZALFA PUTU AYU SAKILA_BAB II.pdf

Download (1MB)
Text
ZALFA PUTU AYU SAKILA_BAB III.pdf
Restricted to Registered users only

Download (958kB)
Text
ZALFA PUTU AYU SAKILA_BAB IV.pdf
Restricted to Registered users only

Download (1MB)
Text
ZALFA PUTU AYU SAKILA_BAB V.pdf
Restricted to Registered users only

Download (864kB)
Text
ZALFA PUTU AYU SAKILA_DAFTAR PUSTAKA.pdf

Download (991kB)
Text
ZALFA PUTU AYU SAKILA_LAMPIRAN.pdf
Restricted to Registered users only

Download (10MB)

Abstract

In building construction projects there are still many problems of inefficiency in the
implementation of the construction process. To overcome this, it is necessary to
improve planning with a lean construction approach, in which waste monitoring is
carried out. therefore the method used in this research is to use the value stream
mapping method which is one of the tools that exist in the concept of lean
construction. In this research, identification or monitoring of waste that has value
added and non-value added will be carried out in the Prof. Hospital Building
construction project. Dr. Margono Soekarjo Purwokwerto. This research was
carried out at week 6 on foundation work. The source of the calculation of the
estimated implementation cost uses project realization volume data. The research
items in amatin are at the P2-C1 pilecap point and BP.101 borepile point. The
results of the analysis of monitoring waste calculations identified Value Added
Activity (VAA) of 81.89%, Non Value Added Activity Necessary (NVAAN) of
3.52%, and Non Value Added Activity Unnecessary (NVAAU) of 14.54%. For the
results of estimated implementation costs for borepile and pilecap foundation work
based on the realized volume of Rp. 52,384,433 and the results of the estimated cost
of implementation on the borepile and pilecap foundation work based on the
planned volume (BoQ) of Rp. 75,571,040. so, the difference from the results of the
estimated cost is Rp. 23,186,607.

Dosen Pembimbing: SUKSMONO, ARIF KURNIAWAN and AFRIANDINI, BESTY | nidn0615037802, nidn0617049201
Item Type: Thesis (S1)
Uncontrolled Keywords: Lean construction, Value Stream Mapping, Borepile, Pilecap
Subjects: T Technology > TA Engineering (General). Civil engineering (General)
Divisions: Fakultas Tekniik Dan Sains > Teknik Sipil S1
Depositing User: Nur Hardiansyah
Date Deposited: 04 Jan 2024 01:08
Last Modified: 04 Jan 2024 01:08
URI: http://repository.ump.ac.id/id/eprint/16087