PRASETYO, HENDAR (2022) OPTIMASI WAKTU DAN BIAYA ALAT BERAT PADA PEKERJAAN ERECTION DENGAN METODE TIME COST TRADE OFF (Studi Kasus Proyek New Factory 1 dan 2 PT. Victoria Beauty Industrial Purbalingga). S1 thesis, Universitas Muhammadiyah Purwokerto.
Hendar Prasetyo_Cover.pdf
Download (2MB)
Hendar Prasetyo_BAB I.pdf
Download (832kB)
Hendar Prasetyo_BAB II.pdf
Download (1MB)
Hendar Prasetyo_BAB III.pdf
Restricted to Registered users only
Download (1MB)
Hendar Prasetyo_BAB IV.pdf
Restricted to Registered users only
Download (1MB)
Hendar Prasetyo_BAB V.pdf
Restricted to Registered users only
Download (828kB)
Hendar Prasetyo_Daftar Pustaka.pdf
Download (939kB)
Hendar Prasetyo_Lampiran.pdf
Restricted to Registered users only
Download (11MB)
Abstract
Because of the major structural component of PT. Victoria Beauty Industrial Purbalingga's new factory 1 and new factory 2 projects are typical steel frames; heavy machinery is required to move or lift steel during the construction of the frames. Lack of time planning in executing the steel frame erection work increases the possibility that the work will not be completed by the ideal time. This research examined the time and cost optimization of heavy equipment for erection work using the time-cost trade-off approach by increasing the number of cranes and extending working hours by an hour. According to the findings, planning for the erection work required 20.72 days and cost Rp. 136,082,784.72. The time acquired was 18.62 days and cost Rp. 137,751,475.31 with a time efficiency of 10.11% and additional costs of 1.23% after adding 1 hour of working hours. It took 10.37 days and cost Rp. 132,787,089.31 to add 2 units of mobile cranes Tadano TL-250e, which resulted in a time efficiency of 49.96% and a cost efficiency of 2.42%. It took 10.35 days and cost Rp 139,378,104.86 with the addition of 2 units of Kato KR-25H mobile cranes, with a time efficiency of 50.04% and additional costs of 2.42%.
| Dosen Pembimbing: | AZIZI, AMRIS and SUKSMONO, ARIF KURNIAWAN | nidn, nidn |
|---|---|
| Item Type: | Thesis (S1) |
| Uncontrolled Keywords: | time cost trade off, optimization, time, cost |
| Subjects: | T Technology > TA Engineering (General). Civil engineering (General) |
| Divisions: | Fakultas Tekniik Dan Sains > Teknik Sipil S1 |
| Depositing User: | Catur Indra Himawan |
| Date Deposited: | 06 Jan 2023 02:58 |
| Last Modified: | 09 Dec 2024 04:17 |
| URI: | http://repository.ump.ac.id/id/eprint/15086 |